Home / Pune / Hinjawadi
Kolte Patil Life Republic

Hinjawadi

WhatsApp_Icon

RERA ID: P52100007511, P52100009640, P52100002682, P52100002646, P52100016987, P52100018539, P52100022154, P52100023317, P52100026426, P52100027629, P52100030072, P52100031799, P52100034733, P52100047921, P52100047317, P52100048241, P52100048624

Recent Transactions
View 8231 Transactions

Disclaimer

BHK Analysis
Last Updated on MahaRERA - 19th Jan 2024

Units Sold

6,962 of 8,097

BHKTotal UnitsUnits Sold% Units Sold
Towers

A

Construction90%

Rera No. : P52100007511

Completion Date : Dec-2019

Units Sold 100%

252  of 252

B

Construction90%

Rera No. : P52100007511

Completion Date : Dec-2019

Units Sold 100%

252  of 252

C

Construction90%

Rera No. : P52100007511

Completion Date : Dec-2019

Units Sold 99%

166  of 168

D

Construction90%

Rera No. : P52100007511

Completion Date : Dec-2019

Units Sold 99%

166  of 168

G

Construction90%

Rera No. : P52100009640

Completion Date : Dec-2022

Units Sold 99%

255  of 258

H

Construction90%

Rera No. : P52100009640

Completion Date : Dec-2022

Units Sold 99%

255  of 258

R2- 18/19

Construction80%

Rera No. : P52100002682

Completion Date : Mar-2019

Units Sold 100%

2  of 2

R2- 20/21

Construction80%

Rera No. : P52100002682

Completion Date : Mar-2019

Units Sold 100%

2  of 2

R2- 22/23

Construction80%

Rera No. : P52100002682

Completion Date : Mar-2019

Units Sold 50%

1  of 2

R2- 118/119

Construction80%

Rera No. : P52100002682

Completion Date : Mar-2019

Units Sold 100%

2  of 2

R2- 120/121

Construction80%

Rera No. : P52100002682

Completion Date : Mar-2019

Units Sold 100%

2  of 2

R2- 122/123

Construction80%

Rera No. : P52100002682

Completion Date : Mar-2019

Units Sold 100%

2  of 2

R2- 9

Construction38%

Rera No. : P52100002682

Completion Date : Mar-2019

Units Sold 0%

0  of 1

A

Construction90%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold 99%

175  of 176

B

Construction90%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold 100%

176  of 176

C

Construction54%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold 77%

133  of 173

D

Construction18%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold 9%

16  of 173

E

Construction90%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold 99%

174  of 176

F

Construction90%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold 100%

176  of 176

G

Construction90%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold 100%

176  of 176

Parking 1

Construction80%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold %

0  of 0

Parking 2

Construction100%

Rera No. : P52100002646

Completion Date : Dec-2027

Units Sold %

0  of 0

Building E

Construction83%

Rera No. : P52100016987

Completion Date : Dec-2022

Units Sold 99%

246  of 249

Building A

Construction90%

Rera No. : P52100018539

Completion Date : Dec-2023

Units Sold 96%

166  of 173

Building B

Construction90%

Rera No. : P52100018539

Completion Date : Dec-2023

Units Sold 95%

164  of 173

Building C

Construction90%

Rera No. : P52100018539

Completion Date : Dec-2023

Units Sold 95%

165  of 173

Building E Shops

Construction90%

Rera No. : P52100018539

Completion Date : Dec-2023

Units Sold 0%

0  of 32

Building E

Construction71%

Rera No. : P52100022154

Completion Date : Dec-2024

Units Sold 98%

173  of 176

Building G

Construction71%

Rera No. : P52100022154

Completion Date : Dec-2024

Units Sold 100%

176  of 176

Parking Building

Construction56%

Rera No. : P52100022154

Completion Date : Dec-2024

Units Sold %

0  of 0

F Building

Construction63%

Rera No. : P52100023317

Completion Date : Dec-2024

Units Sold 99%

258  of 261

City Elanza

Construction22%

Rera No. : P52100026426

Completion Date : Jul-2023

Units Sold 0%

0  of 128

Building A

Construction87%

Rera No. : P52100027629

Completion Date : Dec-2024

Units Sold 95%

243  of 255

Building H

Construction87%

Rera No. : P52100027629

Completion Date : Dec-2024

Units Sold 94%

176  of 187

Building I

Construction60%

Rera No. : P52100027629

Completion Date : Dec-2024

Units Sold 95%

177  of 187

Building G

Construction81%

Rera No. : P52100030072

Completion Date : Sep-2024

Units Sold 91%

171  of 187

Building F

Construction56%

Rera No. : P52100030072

Completion Date : Sep-2024

Units Sold 91%

238  of 261

M

Construction41%

Rera No. : P52100031799

Completion Date : Oct-2025

Units Sold 75%

130  of 173

Building B

Construction36%

Rera No. : P52100034733

Completion Date : Dec-2025

Units Sold 92%

151  of 165

Building C

Construction32%

Rera No. : P52100034733

Completion Date : Dec-2025

Units Sold 93%

150  of 161

Building A

Construction11%

Rera No. : P52100047921

Completion Date : Dec-2026

Units Sold 37%

63  of 172

Building B

Construction22%

Rera No. : P52100047921

Completion Date : Dec-2026

Units Sold 70%

121  of 172

Building C

Construction21%

Rera No. : P52100047921

Completion Date : Dec-2026

Units Sold 60%

104  of 172

Building D

Construction23%

Rera No. : P52100047921

Completion Date : Dec-2026

Units Sold 72%

123  of 172

Shops

Construction27%

Rera No. : P52100047921

Completion Date : Dec-2026

Units Sold 0%

0  of 51

Building D

Construction34%

Rera No. : P52100047317

Completion Date : Dec-2025

Units Sold 88%

208  of 237

Row Houses

Construction29%

Rera No. : P52100048241

Completion Date : Dec-2025

Units Sold 95%

93  of 98

Building E

Construction32%

Rera No. : P52100048624

Completion Date : Dec-2027

Units Sold 32%

93  of 295

Project Summary

QuarterTotal UnitsUnits Sold% Units Sold
Map View

Loading...

Frequently asked questions

The Maharashtra Real Estate Regulatory Authority (MahaRERA), was established under the Real Estate (Regulation and Development) Act 2016 (RERA), through Notification No.23 of the state government. The state's rules under the RERA were formulated as the Maharashtra Real Estate (Regulation and Development)(Registration of real estate projects, Registration of real estate agents, rates of interest and disclosures on website) Rules, 2017.
MahaRERA is the Maharashtra Real Estate Regulatory Authority. It came into existence on May 1, 2017.
A unique identification number given to a specific registered project by RERA authority.
Kolte Patil Life Republic, Kolte Patil Life Republic Twin Bungalows, Kolte Life Republic Lakefront Residences, Megapolis Smart Homes III, Megapolis Sparklet.
The developer for Kolte Patil Life Republic is KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED.
The RERA numbers for Kolte Patil Life Republic are P52100002646, P52100009640, P52100002682, P52100007511, P52100016987, P52100017116, P52100018539, P52100022154, P52100026426, P52100027629, P52100023317, P52100030072, P52100031799, P52100034733, P52100047317, P52100047921, P52100048241, P52100048624.
Kolte Patil Life Republic is located in Hinjawadi. Pincode for the Kolte Patil Life Republic is 411057.
Total apartments in the Kolte Patil Life Republic are 8097 and the different configurations available are 1 BHK, 2 BHK, 3 BHK, 4 BHK, Row House, 3.5 BHK.
Out of 8097 apartments in the Kolte Patil Life Republic, 6962 apartments are sold in the different configurations.
As per RERA, the Kolte Patil Life Republic is getting completed towerwise and completion years are A - 2019, B - 2019, C - 2019, D - 2019, G - 2022, H - 2022, R2- 18/19 - 2019, R2- 20/21 - 2019, R2- 22/23 - 2019, R2- 118/119 - 2019, R2- 120/121 - 2019, R2- 122/123 - 2019, R2- 9 - 2019, A - 2027, B - 2027, C - 2027, D - 2027, E - 2027, F - 2027, G - 2027, Parking 1 - 2027, Parking 2 - 2027, Building E - 2022, Building A - 2023, Building B - 2023, Building C - 2023, Building E Shops - 2023, Building E - 2024, Building G - 2024, Parking Building - 2024, F Building - 2024, City Elanza - 2023, Building A - 2024, Building H - 2024, Building I - 2024, Building G - 2024, Building F - 2024, M - 2025, Building B - 2025, Building C - 2025, Building A - 2026, Building B - 2026, Building C - 2026, Building D - 2026, Shops - 2026, Building D - 2025, Row Houses - 2025, Building E - 2027.
The carpet area for 1 BHK in Kolte Patil Life Republic ranges from 370-450 sqft.
The carpet area for 2 BHK in Kolte Patil Life Republic ranges from 530-720 sqft.
The carpet area for 3 BHK in Kolte Patil Life Republic ranges from 750-1050 sqft.
The carpet area for 4 BHK in Kolte Patil Life Republic ranges from 1610-1610 sqft.
The carpet area for Row House in Kolte Patil Life Republic ranges from 1710-1710 sqft.
The carpet area for 3.5 BHK in Kolte Patil Life Republic ranges from 1590-1590 sqft.

Look at actual transaction prices and decide with confidence!

Get access to 1 cr+ property transactions at your fingertips